Placing dumped riprap on upstream slope of embankment in vicinity of sta. 33+00. Dragline is being used to grade material to the required slope., Original photo number: Pine R - 055
Placing mechanically tamped embankment against left wall of spillway gate structure between stations 5+84 and 6+32., Original photo number: Pine R - 386
Placing embankment in additional cut-off trench. Looking toward right abutment from axis sta. 16+25. Refer to Pine R - 188 and 195., Original photo number: Pine R - 135
Embankment placing in old river channel, where operations are being concentrated at present. The No. 3 section is seen in foreground grading into the downstream No. 2 section near rock-rake and trucks., Original photo number: Pine R - 096
Embankment placing operations looking upstream in temporary diversion channel from right side at sta. 7+75. Shovel is excavating stock-piled material and the bulldozer is spreading it., Original photo number: Pine R - 437
Placing dumped riprap on right side of spillway outlet channel. Darker colored rock was placed during 1939 season., Original photo number: Pine R - 391 a&b
Placing the 12-inch diameter sewer-pipe toe drain. The boards were used to gauge the 6 inches of 3/4-inch to 1.5-inch gravel required to be placed about the pipe. The remainder of the trench was filled with small cobbles., Original photo number: Pine R - 144